Information for Meeting of MART Advisory Board (Montachusett Area Regional Transit)
Wednesday February 19, 2014 10:30 AM EST

Town:Shirley, MA Templeton, MA Athol, MA Lunenburg, MA 
Board:MART Advisory Board (Montachusett Area Regional Transit)
Time:Wednesday February 19, 2014 10:30 AM EST
Location:MART Maintenance/Garage Facility
1427R Water Street, Fitchburg, MA 01420
Agenda:
I.	Call to Order
II.	General Comments.  
III.	Approval of October 31, 2013 Minutes and January 22, 2014 Mintues.
	RESOLUTION 723- BE IT RESOLVED that the Advisory Board of the Montachusett Regional Transit Authority approves the October 31, 2013 minutes as presented.
	RESOLUTION 724- BE IT RESOLVED that the Advisory Board of the Montachusett Regional Transit Authority approves the January 22, 2014 minutes as presented.
IV.	Financial Matters
A.	Status of State Funding
B.	Status of Federal Funding
1. 	Section 5307 Funding
2.	TIGGER II Grant
3. 	State of Good Repair Grant – Buses
4. 	Clean Fuels Grant 
5.	Section 5310 and 5339 Funding
C.	Financial Oversight/Executive Compensation Committee Update		
V.	Administrative Matters

A.	Presentation on the Process for Joining the Massachusetts State Retirement System – Nick Favorito, the Executive Director of the State Retirement Board 
B.	Request from Mohammed Khan’s attorney to discuss State Retirement Potential Over-Earnings Issue and additional request that “In light of the fact that when Mohammed Khan retired in 2003, he was permitted by the Massachusetts Public Retirement Law, Ch. 32; s. 91(a), to go to work for an Authority such as MART, earnings limits in Ch. 32; sec. 91(b) do not apply to him. Therefore, he should be reinstated to his position as Administrator of MART retroactive to January 9, 2014, with full benefits from that date forward”.
VI.	C. 	Finance and Audit Subcommittee recommendation that the MART Advisory Board engage special counsel with expertise in Labor and Employment Law
Capital Equipment/Facilities
A.	North Leominster Commuter Rail Parking Facility
Construction activity since the last board meeting includes substantial completion of the project with the exception of the elevator inspection, some signage and issuance of a temporary or permanent Certificate of Occupancy. Over the past several weeks, there are contractual and legal issues which have essentially shut down the project. MART is working with its attorney on the project to get the work completed and the facility opened.
B.	Improvement to the Commuter Rail Corridor between Fitchburg and Boston 
Work on the project is continuing. The double tracking work along the corridor which resulted in the suspension of weekend service from June through December. The work has now stopped for the winter season but will resume again for the May to November timeframe resulting in the suspension of weekend service again. The MBTA has indicated that this suspended weekend service on the line will occur again in 2015, when the double tracking should be completed. 
C.	Wachusett Commuter Rail Extension Project – Station, Parking and Layover  Facilities
Construction is well underway at both the station and layover sites. MBTA is working on the completion is working with Pan AM on procurement of signal equipment. Pan Am has commenced with the track work for the Wachusett Extension. Substantial project completion is expected in December 2014 with full completion in the spring of 2015. 
D.	Parking Improvement at Ayer-Rail Trail Facility 	
MART staff has continued to meet with the Town Administrator and Economic Development Director for Ayer.  MART has also met with Federal Transit Administration Officials in Cambridge, MA and also met with local stakeholders and the MBTA at the proposed project location. MART is still working with local officials to procure an access between Main Street and the current Train Station in Ayer through private property.  FTA Officials indicated that we have to resolve this access issue as soon as possible before the rest of the project can move forward.  MART will continue to discuss this matter with Ayer Officials for a procurement of an access path, without any easement or any other conditions. MART is also working to arrange a site visit by the MBTA Office of Accessibility to determine potential triggering of full ADA compliance for the station and platform.
VII.	Operational Services and Status Reports
A.	MART Operation Status on Revenue and Ridership
1.	Fitchburg/Leominster
2.	Gardner and Mount Wachusett Community College
3.	ADA Service
4.	Council on Aging (COA)
5.          Veterans/COA Out of Town
6.	Dial-A-MART       
VIII.	HST Status Reports 
A.	MART Negotiations with HST/EOHHS for Statewide Brokerage Contract 
B.	HST Update
IX.	Other Business	
A. 	Littleton Parking Needs Feasibility Study and Preliminary Work
X.	Adjournment
C:	City and Town Clerks: Please post this notice pursuant to MA General Laws Chapter 30A, 
Sections 18-25.
Scheduled By:Amy McDougall
Posted At:Feb 13, 2014 3:17 PM EST
Last Modified:Feb 13, 2014 3:17 PM EST
Minutes:Minutes are not on record with the Town Clerk's office